Hutton Field

 

Scope: Hutton Field opened on March 6, 2008 and is located on north campus.

Specifics

  • Architect: Sportscape International
  • Construction By: Sportscape International
  • Project Managers: Valerie Crooks
  • Construction Start Date: Fall 2007
  • Completion Date: March 2008
  • Gross Square Footage: N/A
  • Cost: $650,000

Status and Construction Updates

07/18/07 Field design in progress; project submitted to City of Thousand Oaks for entitlement.
11/04/07 Field construction is well underway. Rough grading and irrigation completed; fine grading and electrical work in progress.
01/28/08
Field construction is complete! Minor odds and ends, like painting the scoreboard, pending completion.
03/06/08 Project Complete. Opening Ceremony on March 6, 2008
   
   
   
   

 

 

 

 

 




     